About Project

PROJECT SUMMERY
General Petroleum Company (referred here after as GPC) requires to construct two new pipe
lines to connect their existing facilities.
The first line is from Bakr 1 Station to Al-Hamad Processing Station with total length of 2800
Mt. (refereed here after as Line 1)
Second line is from North Amer Station to South Amer Station with total length of 3500 Mt.
(Referred here after as Line 2)
GPC as a CLIENT contracted Egyptian Maintenance Company as a MAIN CONTRACTOR to
execute the project, where EMC conducted a complete engineering design with full profiling
and design of the two required lines and completed the procurement of all required materials.
Total Execution duration of the project is 5 Months from the site receiving date.