EMC- Ras Sudr FF
Investor Name:
Published Date:
Location:
Value:
Architecture:
About Project
5. RESPONSIBILITIES
5.1 CONSTRUCTION SUPERVISOR
Responsible for the implementation of this procedure who shall pass on
instructions down the line to maintain the required quality level at each stage of
construction.
5.2 MECHANICAL FOREMEN
Responsible for the execution of correct working techniques with strict
adherence to this method statement and reference documents.
5.3 SITE SUPERINTENDENTS / FOREMEN
Directly responsible for the Quality produced by the workers under them. They
shall confirm that latest drawings, specifications, grades of materials, correct
tools etc. are used. They shall also guide the workers in the interpretation of
drawings/documents so that the work is carried out in correct sequential
manner, meeting the various in process inspection activities.
5.4 THE FOREMEN
Responsible for deploying qualified welders. They shall also be responsible for
ensuring that the welders withdraw electrodes as per WPS and that they work
within the welding parameters of approved WPS.
5.5 QC INSPECTORS / WELDING INSPECTORS
Responsible for carrying out the in-process Inspection of fabrication,
arrangement for NDT and relevant tests as per ITP’s. They shall also be
responsible for maintaining the documentation & records of inspection.